OVERVIEW

Cyprus is not a member of IATI nor has it joined OGP. However as an EU Member State it is part of the EU’s collective commitment to both the EU Transparency Guarantee and the Busan common standard, of which IATI is a core component. It is yet to publish an implementation schedule. Cyprus has opted out of the EU-13 project for enhancing ODA reporting capacity and systems. Responsibility for CyprusAid shifted from the Planning Bureau to the Ministry of Foreign Affairs in mid-2013, however no new information has been published by the MFA since 2013.

ANALYSIS

Cyprus scores only 5.9%, placing it in the very poor category. It ranks 48th out of 50 bilateral agencies, above only Greece and China. It is the only organisation covered by the Index to score zero for commitment to aid transparency. It does not score any points for organisation-level financial information, the provision of project documents or results and conditions data. CyprusAid’s website notes that its 2006–2010 organisation strategy is extended for the period covering 2011–2015 and includes some information related to allocation of resources. However, no other organisation planning information could be found. Similarly, very limited basic activity information is published. Cyprus does not publish any information in machine-readable formats. It does not score on 32 of the 39 indicators.

RECOMMENDATIONS

  • Cyprus should join IATI and begin publishing to IATI as soon as possible in order to meet the 2015 deadline. It should publish an ambitious implementation schedule, with specific timelines and delivery targets, aiming towards full implementation of the IATI Standard by the end of 2015.
  • In the short term, it should use the EU-DEVFIN platform, which aims to enhance EU-13 ODA reporting capacity and systems, to publish current data in accordance with the IATI Standard. It should work to publish directly from its own systems by the end of 2015.
  • Cyprus should join OGP. This would be an opportunity to share best practice in open data and open government approaches.

Close

DONOR PROFILE

First published to IATI:

N/A

2013 ATI Score:

6.45%

2013 ATI Rank:

62



Visit ATI 2013...

INDICATOR SCORING

TOTAL

5.91%


COMMITMENT TO
AID TRANSPARENCY:

0/10


PUBLICATION
ORGANISATION LEVEL:

2.5/25


PUBLICATION
ACTIVITY LEVEL:

3.41/65

Commitment

1. FOIA

2. Implementation Schedules

3. Accessibility

Publication Status
Source

http://www.rti-rating.org/country_data.php

Comments

No rating found on global RTI rating.


Click here to view history

1. FOIA

Stage

Status

Format

Source

Comments

Researcher
http://www.rti-rating.org/country_data.php
No rating found on global RTI rating.

Donor Review
http://www.rti-rating.org/country_data.php

PWYF Review

Independent Reviewer
Disagree
Cyprus has not yet adopted any right to information legislation. The Ministry of Justice which is in charge of drafting the Expand...relevant legislation has expressed its commitment for pushing forward this process yet it is still to initiate a formal consultation process on this matter.

PWYF Final Assessment
http://www.rti-rating.org/country_data.php
No rating found on global RTI rating.

Publication Status
Source

No data available.

Comments

No Common Standard or IATI implementation schedule found. Cyprus is covered by EU-wide commitments to transparency which include the implementation of the Busan Common Standard.


Click here to view history

2. Implementation schedules

Stage

Status

Format

Source

Comments

Researcher
http://2014tracker.publishwhatyoufund.org/plan/organisations/
No Common Standard or IATI implementation schedule found.

Donor Review
http://2014tracker.publishwhatyoufund.org/plan/organisations/

PWYF Review

Independent Reviewer
Disagree
There has been no commitment by Cyprus to implement the Common Standard

PWYF Final Assessment
No Common Standard or IATI implementation schedule found. Cyprus is covered by EU-wide commitments to transparency which include the implementation of Expand...the Busan Common Standard.

Publication Status
Source

No data available.

Comments

No data portal or project database found.


Click here to view history

3. Accessibility

Stage

Status

Format

Source

Comments

Researcher
N/A
No data portal or project database found.

Donor Review
N/A

PWYF Review

Independent Reviewer
Disagree
Currently no information whatsoever in relation to Cyprus' Aid is published

PWYF Final Assessment
No data portal or project database found.

Planning

Financial

4. Organisation Strategy

5. Annual Report

6. Allocation Policy

7. Procurement Policy

8. Country Strategy

9. Total Budget

10. Disaggregated Budgets

11. Audit

Publication Status

Always

Format: Document

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/all/ACD30B2200A98B00C2257A0600337FEC/$file/%CE%9CEDIUM%20TERM%20STRATEGY.pdf?openelement

Comments

Dated 2006-2010 but website states it will be extended to 2011-2015


Click here to view history

4. Organisation strategy

Stage

Status

Format

Source

Comments

Researcher
Always
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/all/ACD30B2200A98B00C2257A0600337FEC/$file/%CE%9CEDIUM%20TERM%20STRATEGY.pdf?openelement Expand...
Dated 2006-2010 but website states it will be extended to 2011-2015

Donor Review
Always
Document

PWYF Review
Always
Document

Independent Reviewer
Disagree
Document
Following a transfer of all responsibilities relating to the implementation of Cyprus's Development Aid (including publication of all related information) from Expand...the Planning Bureau to the Foreign Ministry in May 2013 there have been no updates on any aspect of development aid. The old website managed by the Planning Bureau is still there but without updates. A default statement on the old website that is still accessible stated that the 2006-2010 development policy was renewed until 2015. But that is all the information one has to go by. The FM has not inaugurated a new website to reflect the fact that it has competence over both policy making and implementation in regard to Cyprus' ODA.

PWYF Final Assessment
Always
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/all/ACD30B2200A98B00C2257A0600337FEC/$file/%CE%9CEDIUM%20TERM%20STRATEGY.pdf?openelement Expand...
Dated 2006-2010 but website states it will be extended to 2011-2015

Publication Status

Not Published

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page11_en/page11_en?OpenDocument

Comments

ODA statistics are published by year but no annual report could be found.


Click here to view history

5. Annual report

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page11_en/page11_en?OpenDocument
ODA statistics are published by year but no annual report could be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document
ODA broad statistics were published for the last time in 2012. Since the transfer of responsibility shifted to FM there have Expand...been no updates of any kind.

PWYF Final Assessment
Not published
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page11_en/page11_en?OpenDocument
ODA statistics are published by year but no annual report could be found.

Publication Status

Always

Format: Document

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page06_en/page06_en?OpenDocument

Comments

The medium term strategy for development assistance 2006-2010 has brief information on allocation. The website states that the strategy has been extended to the period of 2011-2013.


Click here to view history

6. Allocation policy

Stage

Status

Format

Source

Comments

Researcher
Always
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page06_en/page06_en?OpenDocument
The medium term strategy for development assistance 2006-2010 has brief information on allocation. The website states that the strategy has been Expand...extended to the period of 2011-2013.

Donor Review
Always
Document

PWYF Review
Always
Document

Independent Reviewer
Disagree
Document
The 2006-2010 strategy was readopted until 2015.

PWYF Final Assessment
Always
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page06_en/page06_en?OpenDocument
The medium term strategy for development assistance 2006-2010 has brief information on allocation. The website states that the strategy has been Expand...extended to the period of 2011-2013.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

7. Procurement policy

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document
Cyprus Aid silent on procurement. This was explained in the past as an outcome of the fact that Cyprus Aid implements Expand...aid related projects through delegated cooperation.

PWYF Final Assessment
Not published
Document
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

The website lists partner/priority countries but does not explain the overarching strategy for any of these countries individually.


Click here to view history

8. Country strategy

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
The website lists partner/priority countries but does not explain the overarching strategy for any of these countries individually.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
The website lists partner/priority countries but does not explain the overarching strategy for any of these countries individually.

Publication Status
Source

No data available.

Comments

This information could not be found.


Click here to view history

9. Total budget

Stage

Status

Format

Source

Comments

Researcher
This information could not be found.

Donor Review

PWYF Review

Independent Reviewer
Disagree
No information has been published since 2012.

PWYF Final Assessment
This information could not be found.

Publication Status
Source

No data available.

Comments

This information could not be found.


Click here to view history

10. Disaggregated budgets

Stage

Status

Format

Source

Comments

Researcher
This information could not be found.

Donor Review

PWYF Review

Independent Reviewer
Disagree
Cyprus aid never published disaggregated budgets.

PWYF Final Assessment
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

11. Audit

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document
An audit has never been published.

PWYF Final Assessment
Not published
Document
This information could not be found.

Basic

Classifications

Financial

Performance

12. Implementer

13. Unique ID

14. Title

15. Description

16. Planned Dates

17. Actual Dates

18. Current Status

19. Contact Details

20. Collaboration Type

21. Flow Type

22. Aid Type

23. Finance Type

24. Sector

25. Sub-national Location

26. Tied Aid Status

33. Budget

34. Commitments

35. Disbursements And Expenditure

36. Budget Identifier

37. Results

38. Impact Appraisals

39. Conditions

Publication Status

Not Published

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument

Comments

Partner organisations are sometimes mentioned in project description but implementer of the project is not explicitly stated.


Click here to view history

12. Implementer

Stage

Status

Format

Source

Comments

Researcher
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument
Partner organisations are sometimes mentioned in project description but implementer of the project is not explicitly stated.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument
Partner organisations are sometimes mentioned in project description but implementer of the project is not explicitly stated.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found for any of the projects assessed.


Click here to view history

13. Unique ID

Stage

Status

Format

Source

Comments

Researcher
Not published
This information could not be found for any of the projects assessed.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
This information could not be found for any of the projects assessed.

Publication Status

Always

Format: Website

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/D69B4625E93929DEC2257A07004C4317?OpenDocument

Comments

Published as part of project description. Note: There is only one ongoing activity in the ""Bosnia and Herzegovina"" which was the donor's largest recipient in 2013 and one ongoing activity in the Caribbean which was the donor's largest recipient in 2012. Hence, 5 randomly selected projects marked ""ongoing"" have been used to determine whether information is 'always', 'sometimes' or 'not published.' The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.


Click here to view history

14. Title

Stage

Status

Format

Source

Comments

Researcher
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/D69B4625E93929DEC2257A07004C4317?OpenDocument Expand...
Published as part of project description. Note: There is only one ongoing activity in the ""Bosnia and Herzegovina"" which was the donor's Expand...largest recipient in 2013 and one ongoing activity in the Caribbean which was the donor's largest recipient in 2012. Hence, 5 randomly selected projects marked ""ongoing"" have been used to determine whether information is 'always', 'sometimes' or 'not published.'

Donor Review
Always
Website

PWYF Review
Always
Website

Independent Reviewer
Disagree
No information has been published since 2012

PWYF Final Assessment
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/D69B4625E93929DEC2257A07004C4317?OpenDocument Expand...
Published as part of project description. Note: There is only one ongoing activity in the ""Bosnia and Herzegovina"" which was the Expand...donor's largest recipient in 2013 and one ongoing activity in the Caribbean which was the donor's largest recipient in 2012. Hence, 5 randomly selected projects marked ""ongoing"" have been used to determine whether information is 'always', 'sometimes' or 'not published.' The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.

Publication Status

Always

Format: Website

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/D69B4625E93929DEC2257A07004C4317?OpenDocument

Comments

The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.


Click here to view history

15. Description

Stage

Status

Format

Source

Comments

Researcher
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/D69B4625E93929DEC2257A07004C4317?OpenDocument Expand...

Donor Review
Always
Website

PWYF Review
Always
Website

Independent Reviewer
Disagree
But note that no updates have been made since 2012

PWYF Final Assessment
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/D69B4625E93929DEC2257A07004C4317?OpenDocument Expand...
The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.

Publication Status

Not Published

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument

Comments

Project profiles currently have information only on the start and end year. Both month and year are needed to score.


Click here to view history

16. Planned dates

Stage

Status

Format

Source

Comments

Researcher
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument
Project profiles currently have information only on the start and end year. Both month and year are needed to score.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument
Project profiles currently have information only on the start and end year. Both month and year are needed to score.

Publication Status

Not Published

Source

No data available.

Comments

Only one set of dates provided. These are assumed to be the planned dates.


Click here to view history

17. Actual dates

Stage

Status

Format

Source

Comments

Researcher
Not published
Only one set of dates provided. These are assumed to be the planned dates.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
Only one set of dates provided. These are assumed to be the planned dates.

Publication Status

Sometimes

Format: Website

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument

Comments

For all projects listed, the current status is marked as either ongoing or completed. Some projects with end dates of 2012 are still marked ongoing and there is not information available on whether and when these projects were extended. Hence this indicator has been scored 'sometimes published.' The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.


Click here to view history

18. Current Status

Stage

Status

Format

Source

Comments

Researcher
Sometimes
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument Expand...
For all projects listed, the current status is marked as either ongoing or completed. Some projects with end dates of 2012 Expand...are still marked ongoing and there is not information available on whether and when these projects were extended. Hence this indicator has been scored 'sometimes published.'

Donor Review
Sometimes
Website

PWYF Review
Sometimes
Website

Independent Reviewer
Disagree
Nothing has been updated since 2012. It is impossible to know whether the expressed commitments for 2013 were met as no Expand...updates were ever given in relation to the intentions and commitments previously expressed.

PWYF Final Assessment
Sometimes
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument Expand...
For all projects listed, the current status is marked as either ongoing or completed. Some projects with end dates of 2012 Expand...are still marked ongoing and there is not information available on whether and when these projects were extended. Hence this indicator has been scored 'sometimes published.' The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.

Publication Status

Not Published

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/contact_en/contact_en?OpenDocument

Comments

Although there is a contact page accessible from the activity pages, this does not contain any contact details, therefore this indicator has been scored 'not published'.


Click here to view history

19. Contact details

Stage

Status

Format

Source

Comments

Researcher
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/contact_en/contact_en?OpenDocument
Although there is a contact page accessible from the activity pages, this does not contain any contact details, therefore this indicator Expand...has been scored 'not published'.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/contact_en/contact_en?OpenDocument
Although there is a contact page accessible from the activity pages, this does not contain any contact details, therefore this indicator Expand...has been scored 'not published'.

Publication Status

Always

Format: Website

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page08_en/page08_en?OpenDocument

Comments

The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.


Click here to view history

20. Collaboration Type

Stage

Status

Format

Source

Comments

Researcher
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page08_en/page08_en?OpenDocument

Donor Review
Always
Website

PWYF Review
Always
Website

Independent Reviewer
Disagree
It was published until 2012. As repeated throughout this questionnaire there have been no updates since 2012.

PWYF Final Assessment
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page08_en/page08_en?OpenDocument
The website appears to have been last updated in December 2013. It notes that TA has been temporarily suspended.

Publication Status

Always

Format: Website

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page03_en/page03_en?OpenDocument

Comments

All aid is ODA as specified in page accessible through the link provided alongside. The website appears to have been last updated in December 2013.


Click here to view history

21. Flow Type

Stage

Status

Format

Source

Comments

Researcher
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page03_en/page03_en?OpenDocument
All aid is ODA as specified in page accessible through the link provided alongside.

Donor Review
Always
Website

PWYF Review
Always
Website

Independent Reviewer
Disagree
The website listed is no longer the designated website for CyprusAid - the specific page announces that since mid 2013 the Expand...responsibility has shifted to the Foreign Ministry. Yet there is no updates on the website of the FM neither has a new site been inaugurated to this end.

PWYF Final Assessment
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/page03_en/page03_en?OpenDocument
All aid is ODA as specified in page accessible through the link provided alongside. The website appears to have been last Expand...updated in December 2013.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

22. Aid Type

Stage

Status

Format

Source

Comments

Researcher
Not published
This information could not be found.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree
This was published up to 2012. Nothing since.

PWYF Final Assessment
Not published
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

23. Finance Type

Stage

Status

Format

Source

Comments

Researcher
Not published
This information could not be found.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

Sectors are not explicitly and separately mentioned for any project even if they are sometimes implied in the title.


Click here to view history

24. Sector

Stage

Status

Format

Source

Comments

Researcher
Not published
Sectors are not explicitly and separately mentioned for any project even if they are sometimes implied in the title.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
Sectors are not explicitly and separately mentioned for any project even if they are sometimes implied in the title.

Publication Status

Sometimes

Format: Website

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument

Comments

This information does not appear to be published consistently.


Click here to view history

25. Sub-national location

Stage

Status

Format

Source

Comments

Researcher
Sometimes
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument Expand...
This information does not appear to be published consistently.

Donor Review
Sometimes
Website

PWYF Review
Sometimes
Website

Independent Reviewer
Disagree

PWYF Final Assessment
Sometimes
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument Expand...
This information does not appear to be published consistently.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

26. Tied Aid Status

Stage

Status

Format

Source

Comments

Researcher
Not published
This information could not be found.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

27. MoU

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

28. Evaluations

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
This information could not be found.

Publication Status

Sometimes

Format: Document

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument

Comments

Upon review of the evidence, not all projects were found to have objectives sufficiently detailed to meet the requirements of the scoring guidelines.


Click here to view history

29. Objectives

Stage

Status

Format

Source

Comments

Researcher
Always
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument Expand...
All current projects sampled have stated objectives.

Donor Review
Always
Document

PWYF Review
Always
Document

Independent Reviewer
Disagree
Document
Agree in so far as past projects are concerned. As explained there have been no updates on Cyprus's ODA since 2012. Expand...So it is unclear whether there have been any funding of projects since and what the objectives of those projects are.

PWYF Final Assessment
Sometimes
Document
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument Expand...
Upon review of the evidence, not all projects were found to have objectives sufficiently detailed to meet the requirements of the Expand...scoring guidelines.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

30. Budget Docs

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

31. Contracts

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

32. Tenders

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
This information could not be found.

Publication Status

Not Published

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument

Comments

The budget for one project is listed by year but only retrospectively, so it does not score for this indicator.


Click here to view history

33. Budget

Stage

Status

Format

Source

Comments

Researcher
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument
The budget for one project is listed by year but only retrospectively, so it does not score for this indicator.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument
The budget for one project is listed by year but only retrospectively, so it does not score for this indicator.

Publication Status

Always

Format: Website

Source

http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument

Comments

Listed for all projects. The website appears to be last updated in December 2013.


Click here to view history

34. Commitments

Stage

Status

Format

Source

Comments

Researcher
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument Expand...
Listed for all projects.

Donor Review
Always
Website

PWYF Review
Always
Website

Independent Reviewer
Disagree
But no updated information is available

PWYF Final Assessment
Always
Website
http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/AF9F2784A804E327C2257A06002EDDA6?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/C5F49108A7B133E6C2257A06002EF3B0?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/4AA2213D52840562C2257A06002EED1F?OpenDocument http://www.cyprusaid.gov.cy/planning/cyprusaid.nsf/All/9F28B8AF1F52C4F3C2257A06002EE9AF?OpenDocument Expand...
Listed for all projects. The website appears to be last updated in December 2013.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

35. Disbursements and expenditure

Stage

Status

Format

Source

Comments

Researcher
Not published
This information could not be found.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

36. Budget Identifier

Stage

Status

Format

Source

Comments

Researcher
Not published
This information could not be found.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

37. Results

Stage

Status

Format

Source

Comments

Researcher
Not published
This information could not be found.

Donor Review
Not published

PWYF Review
Not published

Independent Reviewer
Disagree

PWYF Final Assessment
Not published
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

38. Impact Appraisals

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
This information could not be found.

Publication Status

Not Published

Source

No data available.

Comments

This information could not be found.


Click here to view history

39. Conditions

Stage

Status

Format

Source

Comments

Researcher
Not published
Document
This information could not be found.

Donor Review
Not published
Document

PWYF Review
Not published
Document

Independent Reviewer
Disagree
Document

PWYF Final Assessment
Not published
Document
This information could not be found.